Fit-out of new Tier 4 Data Hall complete with multiple data racks , 5MVA power supply, UPS back‐up system, and 3 No. 2 MVA back up generators. The project was completed within a tight programme of ten weeks and included structural upgrade works to an existing warehouse facility.