Description:
Fit-out of new Tier 4 Data Hall complete with multiple data racks , 5MVA power supply, UPS back‐up system, and 3 No. 2 MVA back up generators. The project was completed within a tight programme of ten weeks and included structural upgrade works to an existing warehouse facility.
Technical Details:
- 5 MVA Power Supply
- 3 x 2 MVA Back‐up Generators
- 9 Air Handling Units
- Redundancy Level N + 1
- Tier 4 Classification